Construction supervision of a bank's main data centre

Client-side advisor during the construction of a bank's main production data centre - design reviews, site visits, contractor oversight and commissioning advice.

Challenge

A bank was building its new main production data centre but had no in-house data centre expertise. It wanted a trusted advisor on its side to protect its interests throughout the detailed design and construction. I had worked for the same bank before, on its data centre strategy and concept design.

Approach

As trusted advisor to the bank, I:

  • reviewed the contractor’s proposal for gaps against the bank’s requirements;
  • attended the detailed design workshops on layout, electrical systems, cooling, connectivity and security;
  • reviewed design submittals and recommended acceptance or rejection;
  • reviewed the contractor’s planning and monitored progress;
  • advised on adherence to industry standards and best practices;
  • visited the construction site and helped resolve technical issues;
  • reviewed contractor invoices and advised on the release of payments;
  • protected the bank against scope creep;
  • advised on acceptance during testing and commissioning;
  • reported to management every month.

Result

A bank that stayed in control of its data centre project, with an independent expert to check quality, scope and costs.